Free Training: Construction Schedule Risk Mitigation Strategies
Published June 2021, Updated April 2023
Published July 2021, Updated January 2024
So what does this mean for you?
This is what the government uses throughout the project to determine earnings for progress payments.
In the sections below, we’re providing insight and tips for the cost-loaded schedule requirements per the standard UFGS 01 32 01.00 10 specification, including:
Navigating schedule cost loading for federal projects can be challenging. This article simplifies the process, providing guidance and tips to ensure compliance and optimize project management.
From the contractor’s perspective, the requirements we’re discussing are important because if the schedule isn’t compliant, it can be rejected cause delays in progress payments due to the direct link from the schedule to payment.
From the government’s perspective, these requirements are important because they balance project risk. For both parties, the cost loading requirements also provide a level of flexibility for schedule management.
If your contract includes a requirement similar to the section below (from the standard UFGS 01 32 01.00 10 specification), your project requires the schedule to serve as the basis for progress payments.
Activity costs must be reasonable, and without front-end loading.
Figure 2
Figure 1
Reasonable Cost Loading without Front Loading
If you’re asking - what constitutes “reasonable”? Our recommendation is to distribute costs among work-in-place activities, or those which represent placement, installation, or work performed.
When these activities take place, the government can acquire title to that work through the progress payment process (FAR 52.232-16, FAR 32.503-14).
Avoid front-loading your schedule by ensuring costs are evenly distributed throughout the entire contract period, including costs for commissioning, testing, inspections, and punch list activities.
Cost loading can be reviewed for reasonableness and front-end loading by sorting activities by cost and reviewing the values assigned throughout the project. Take note of activities that have disproportionate amounts, or work-in-place activities that don’t have any costs assigned but should.
The project’s S-Curve can also visually indicate if there is front loading. Schedules with significant costs upfront create a bump earlier in the curve (Figure 1) than if the costs were more evenly distributed (Figure 2).
For O&M manuals, they need to be cost-loaded not less than $20K.
And as described in the section below, payment will be provided once the government approves the submittal, not when the contractor submits.
The specs speak specifically to as-built drawings and O&M manuals as cost-loaded closeout deliverables.
As-built drawings need to be cost loaded not less than $35K, or 1% of the present contract value, whichever is greater, up to $200K.
1% of the contract value needs to be assigned to the “Correction of Punch List from Government Pre-Final Inspection” activity. (This is also a Mandatory Task described in the standard specifications).
This requirement balances risk for the government by having these costs designated towards the end of the project and to ensure the punch list correction takes place.
As an upside however for both parties, it also provides a level of flexibility when statusing activities and schedule management as explained in our article here.
The first step to balance CLINs is to create the Standard Activity Coding Structure as explained in our USACE SDEF Explained article and assign the codes to all activities.
Once the CLIN activity codes have been applied, you can group and sort within the scheduling program to assign costs and ensure they add up to the total amount of each CLIN.
If you’re working with a USACE project that uses RMS (USACE’s Resident Management System), CLIN balancing is especially important. RMS will kick back the schedule when you try to upload if it the CLINs aren’t balanced.
For a more detailed step-by-step process on balancing CLINs in a project schedule, see our article here.
A project’s Contract Line Item Numbers, or CLINs, represent a portion and cost of the contract. A portion of the contract could be a service, a product, or a combination of both.
All project CLINs have their own value, and when you add them up, it equals the total contract value.
The requirement below speaks to the total value of all activities coded to a CLIN activity code needing to equal the value of that CLIN – in other words, “balanced”.
A cost loaded schedule has costs assigned to activities throughout the project. By assigning these costs, teams can better forecast and monitor project expenses, identify potential budget overruns, and evaluate project progress against the financial plan.
A cost-loaded schedule combines schedule activities and their costs, giving a clear picture of how money is spent over time. This helps teams manage budgets, plan for expenses, and track progress, making project management smoother and more efficient.
Cost loaded schedules offer benefits for managing projects by giving a clearer picture of how resources will be used over time. They also make tracking progress easier especially using S-Curves, so teams can spot issues, risks, and make adjustments as needed.
Specific cost loading requirements for military or federal construction project may include limitations on front loading and early activities, required costs for specific close-out documents, required costs for punch list correction, and correct balancing of the contract’s line item numbers (CLINs).
The snapshot below is an example of what a cost loaded schedule looks like. There are budgeted costs assigned to each activity. Since this is a military construction schedule, each activity is also assigned to a project-level activity code that groups the activities by the project’s contract line item number, or CLIN. The total cost of activities coded to each CLIN needs to equal that CLINs value as stated in the contract.
When your contract requires the schedule to serve as the basis for progress payments, instead of having a separate schedule of values and project schedule, they’re combined into a single cost-loaded project schedule.
It’s important the cost-loading requirements are successfully executed in the schedule, so that:
This article shared insight and tips for cost-loading schedule requirements per the standard UFGS 01 32 01.00 10 specification, including reasonable costs without front loading, closeouts, punch list correction, and CLIN balancing.
Questions or comments? Reach us at connect@cpm-ss.com.
Thanks for reading.
Related Articles:
New to USACE Schedules? 3 Things to Know
S-Curve from a Construction Schedule (with Examples)
How to Balance CLINs in a MILCON Schedule
P6 Mandatory Requirements
Receive practical, actionable training and tools, including specialized templates and instruction for military and federal construction projects.
Have any questions?
We'd love to hear from you.
Get started for free with our collection of resources and in-depth articles on scheduling to enhance your success.
Feel confident in your project schedule by ensuring it’s reliable, contractually compliant, and utilized as a tool to minimize risk.
Whenever you’re ready, there are 3 ways we can help:
This blog is for general informational purposes only and is not to be considered an official interpretation or enforcement policy of the UFGS standard specifications. As individual project requirements vary, refer to your specific contract. See our Terms and Conditions and Disclaimer for additional information.
Starting with a new software can be quite intimidating, and Primavera P6 is no exception, especially if you're a newcomer. Traditional training methods can involve lengthy sessions, travel, and...
How to Learn Primavera P6 Quickly: A Beginner's Guide
Successful alignment of the project schedule and quality control system ensures a smooth start of the first phase of the 3 Phase Quality Control system. Also, it enables accurate monitoring of...
USACE Series Part 2:
Schedule and Quality Control
USACE Series Part 1:
Schedule and Progress Payments
The Schedule of Values and Construction Schedule are combined into a single Cost-Loaded Project Schedule, used to determine progress payments and provide placement projections...
Free Checklist
As the government or contractor, quickly and easily confirm your USACE schedule’s cost loading compliance with the 01 32 01.00 10 scheduling specifications.
Navigation
Legal
Offices located in West Granby, CT, and Forest Hill, MD
Founded in 2018 to specialize in schedule consulting and training for military construction.
Copyright 2024 CPM Schedule Solutions LLC. All Rights Reserved.
Contact Us
Free Cheat Sheet
Learn the 5 steps to link the schedule to the submittal register in RMS for USACE projects to improve visibility and minimize the risk of delays due to late or overlooked submittals.