Blog Title

Published June 2021, Updated April 2023

Schedule Specification Percent Complete

Schedule Status Flexibility

Published September 2022, Updated March 2024

Summary

The standard UFGS 01 32 01.00 10 scheduling specification contains a section that allows schedule activities to be considered 100% complete if the remaining work:


  • is considered as punch list items, and
  • doesn’t hold up successor work.


This flexibility provided for schedule management can be used to simplify the schedule updating and review process while not compromising schedule accuracy.


Review your project specifications to see if this section is included – it may make the schedule management aspect of your project easier.


Questions or comments? Reach us at connect@cpm-ss.com.


Thanks for reading.


Related Articles:

How to Learn Primavera P6 Quickly: A Beginner's Guide

Why Quality Construction Schedules Matter

Rule of Thumb: Schedule Level of Detail

Schedule Cost Loading

Schedule Cost Loading Closeout Activities

How to leverage this requirement for schedule management.


This flexibility is described in the specification to “allow for proper schedule management”. As explained in the example scenario above, it simplifies the schedule updating and review process without compromising schedule accuracy.


Also, as explained in our Schedule Cost Loading article, the same specification also includes the requirement for 1% of the contract value to be cost loaded on the “Correction of Punch List from Government Pre-Final Inspection” activity. This cost requirement helps balance risk for the government, allowing this statusing flexibility.


Schedule sequence

Method 2 (USING this spec section): With this method, the painting activity is statused as 100% and closed out – as long as the government agrees that the remaining work is considered a punch list activity, AND it does not hold up the successor flooring*.


*Note the spec section states an activity *may* be declared 100% complete, not *will* - providing the allowance, but not the obligation.


Since the activity is marked as complete, the schedule would not require logic changes to address what would otherwise become an out-of-sequence condition or continue to track the activity as open. The activity’s actual duration would also align more closely with its planned or original duration.


Schedule sequence - activity remaining open

This article discusses a section of the UFGS 01 32 01.00 10 scheduling specification used in federal and military construction projects that is often overlooked, however is helpful with schedule management because of the flexibility it provides.


A schedule activity may be considered 100% complete if the remaining work is considered as punch list items and doesn’t hold up successor work.


Why is this important? The flexibility permitted by this specification section allows the schedule updating and review process to be simplified without compromising schedule accuracy – benefitting the contractor updating the schedule and the owner performing the review.


This article discusses:


  • Where this section is found in the standard scheduling specification.
  • An example scenario where it could apply.
  • How to leverage this requirement for schedule management.



Specification Section 3.3.17 - Percent Complete


The standard UFGS 01 32 01.00 10 schedule specification includes this section as 3.3.17, titled “Percent Complete”. This specification may be used by federal agencies including USACE, NAVFAC, AFCEC, and NASA. (As individual project requirements vary, review your specifications to confirm if this section is included).


During construction, the interior painting finishes, however there’s a small area that needs repainting after it was scratched when the painting subcontractor removed their ladder. This touch-up area is not holding up any successor work, including the start of the flooring installation.


The schedule painting activity can be statused one of two ways:


Method 1 (NOT using this spec section): The activity is statused at 97% complete and will remain open until the paint touch-up is complete, resulting in the following:


  • The schedule will require logic changes to address what will become an out-of-sequence condition since the flooring can start before the painting activity finishes.

  • The painting activity will remain open until the touch-up is complete, requiring the project team to revisit this open activity and status every update until it is closed.

  • If the touch-up remains open for multiple updates, it’s duration would become overrun. For example, instead of the painting taking 10 work days per it’s original duration, it’s actual duration becomes 100 work days.


Schedule sequence

What is an example scenario where this could apply?


As an example - say your project schedule shows that once interior painting completes, flooring installation starts.


Schedule Percent Complete

Training + Tools


Receive practical, actionable training and tools, including specialized templates and instruction for military and federal construction projects.

Have any questions? 

We'd love to hear from you.

Check CircleFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)
Check CircleFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)
Check CircleFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)

Blog + Free Resources


Get started for free with our collection of resources and in-depth articles on scheduling to enhance your success.

Consulting


Feel confident in your project schedule by ensuring it’s reliable, contractually compliant, and utilized as a tool to minimize risk.

Whenever you’re ready, there are 3 ways we can help:

This blog is for general informational purposes only and is not to be considered an official interpretation or enforcement policy of the UFGS standard specifications. As individual project requirements vary, refer to your specific contract. See our Terms and Conditions and Disclaimer for additional information.

Starting with a new software can be quite intimidating, and Primavera P6 is no exception, especially if you're a newcomer. Traditional training methods can involve lengthy sessions, travel, and...
How to Learn Primavera P6 Quickly

How to Learn Primavera P6 Quickly: A Beginner's Guide

Successful alignment of the project schedule and quality control system ensures a smooth start of the first phase of the 3 Phase Quality Control system. Also, it enables accurate monitoring of...
USACE Schedule and Quality Control

USACE Series Part 2: 

Schedule and Quality Control

USACE Cost Loaded Project Schedule

USACE Series Part 1: 

Schedule and Progress Payments

The Schedule of Values and Construction Schedule are combined into a single Cost-Loaded Project Schedule, used to determine progress payments and provide placement projections...
RECENT ARTICLES

Free Checklist

CHECKLIST - USACE SCHEDULE COST LOADING

As the government or contractor, quickly and easily confirm your USACE schedule’s cost loading compliance with the 01 32 01.00 10 scheduling specifications.

USACE Schedule Cost Loading Checklist
    Small Business CPM Schedule

    Navigation

    Legal

    EnvelopeFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)

    Offices located in West Granby, CT, and Forest Hill, MD

    Founded in 2018 to specialize in schedule consulting and training for military construction.


    CPM Schedule Solutions LLC

    Copyright 2024 CPM Schedule Solutions LLC. All Rights Reserved.

    Contact Us