Published June 2021, Updated April 2023
Successfully executing these requirements as the contractor for the government to review and accept is critical for cash flow early on in the project – for the contractor performing the work, and for the government’s supervision and administration (S&A) charges.
This article talked about 3 things to know about construction schedules if you’re new to U.S. Army Corps of Engineers (USACE) projects as a contractor or a new government employee. These topics are important to understand because if they’re overlooked or not executed correctly the project could end up with issues or delays in progress payments.
3 Things to Know:
Questions or comments? Reach us at connect@cpm-ss.com.
Thanks for reading.
Related Articles:
USACE Series Part 1: Schedule and Progress Payments
USACE Series Part 2: Schedule and Quality Control
USACE Series Part 3: Schedule and Submittal Register
How to Balance CLINs in a MILCON Schedule
Schedule Cost Loading
USACE SDEF Explained
Because schedules directly influence so many other parts of the contract administrative processes, they are a critical and powerful project management tool.
If the schedule doesn’t meet the requirements, the government can reject progress payments and also withhold. This importance of the schedule’s relationship to the contractor being able to get paid cannot be understated.
As we talked about in our Schedule Cost Loading article, the schedule serves as the basis for progress payments.
Federal projects typically have more schedule related requirements and restrictions than non-federal projects, and the extent of these requirements can catch you off guard as a new contractor or government employee if you’re not already familiar with them.
The standard 01 32 01.00 10 scheduling specification is 23 pages long, longer than what you may be used to - and has specific requirements (and limitations) on what’s in the schedule, how it’s calculated, how it needs to perform, and the process for submission.
For example:
These examples are only a handful of the requirements. As the contractor developing the schedule or the government performing the reviews, ensure your schedule folks are trained and ready to work with these requirements – early on in the project too.
The Preliminary Project Schedule is the first schedule due to the government, 15 calendar days after Notice to Proceed (NTP). This is followed by the Initial Project Schedule, due 42 calendar days after NTP (these durations may be customized though from the standard specification).
The schedule requirements need to be captured in the first and every schedule submission to follow – the specifications don’t allow for a “rolling wave” approach to gradually include them all.
This article talks about 3 things to know about construction schedules if you’re new to U.S. Army Corps of Engineers (USACE) projects as a contractor or a new government employee.
If you’re coming from the private sector, you may be surprised to learn how many requirements, restrictions, and overall level of oversight there is for USACE project schedules. The schedule requirements are important to understand because if they’re overlooked or not executed correctly you could end up with project issues or delays in progress payments - which isn’t good for anyone.
The requirements we talk about in this article are from the standard UFGS 01 32 01.00 10 specification, which is typically used for USACE projects with any level of complexity. While we’re focusing on USACE projects for this article, these requirements may also apply to other agencies using this specification, including NAVFAC, AFCEC, NASA, and the VA.
3 Things to Know:
Note: As with all our articles, the following is provided for informational use only and does not supersede any specifications or contract requirements provided by USACE.
After these links have been made, every time a schedule update is uploaded into RMS, the submittal register’s “need-by” dates will auto-populate with any new dates from the current schedule information. This provides the contractor and government visibility on which submittals need to be prioritized, decreasing the chance of delays due to late or overlooked submittals.
Quality Control and Quality Assurance. The schedule is also a critical tool to drive the contractor’s Quality Control (QC) and the government’s Quality Assurance (QA) processes.
The contractor’s Quality Control Plan includes a Definable Features of Work (DFOW), which is a listing of separate and distinct groupings of work. The DFOW is used as the basis for developing the schedule’s feature of work (FOW) activity coding structure that needs to be applied to all activities.
Once the FOW codes have been applied to the schedule activities, they can be grouped and sorted to see when the first activity for each feature of work is starting. This allows the QC and QA staff to plan for the Three Phase Control System, including the Preparatory Phase (making sure the site and submittals are ready to have the work begin), the Initial Phase (to include the first inspection), and the Follow-Up Phase (with monitoring and additional inspections).
Receive practical, actionable training and tools, including specialized templates and instruction for military and federal construction projects.
Have any questions?
We'd love to hear from you.
Get started for free with our collection of resources and in-depth articles on scheduling to enhance your success.
Feel confident in your project schedule by ensuring it’s reliable, contractually compliant, and utilized as a tool to minimize risk.
Whenever you’re ready, there are 3 ways we can help:
This blog is for general informational purposes only and is not to be considered an official interpretation or enforcement policy of the UFGS standard specifications. As individual project requirements vary, refer to your specific contract. See our Terms and Conditions and Disclaimer for additional information.
Starting with a new software can be quite intimidating, and Primavera P6 is no exception, especially if you're a newcomer. Traditional training methods can involve lengthy sessions, travel, and...
How to Learn Primavera P6 Quickly: A Beginner's Guide
Successful alignment of the project schedule and quality control system ensures a smooth start of the first phase of the 3 Phase Quality Control system. Also, it enables accurate monitoring of...
USACE Series Part 2:
Schedule and Quality Control
USACE Series Part 1:
Schedule and Progress Payments
The Schedule of Values and Construction Schedule are combined into a single Cost-Loaded Project Schedule, used to determine progress payments and provide placement projections...
Free Checklist
As the government or contractor, quickly and easily confirm your USACE schedule’s cost loading compliance with the 01 32 01.00 10 scheduling specifications.
Navigation
Legal
Offices located in West Granby, CT, and Forest Hill, MD
Founded in 2018 to specialize in schedule consulting and training for military construction.
Copyright 2024 CPM Schedule Solutions LLC. All Rights Reserved.
Contact Us