Published June 2021, Updated April 2023
Published January 2023, Updated July 2024
In this article, you’re going to learn what schedule calendars are, what they look like with examples, and through a variety of scenarios understand the calendar importance for an accurate and reliable schedule.
Source: UFGS 01 32 17.00 20, Updated May 2018
Source: UFGS 01 32 16.00 20, Updated August 2018
From 01 32 17.00 20 (Cost-Loaded Network Analysis Schedules / NAS):
Source: UFGS 01 32 01.00 10, Updated Februay 2015
Construction schedules for military and federal projects are required to use schedule calendars that block out the days specified in the contract, such as weekends, federal holidays, and weather days.
The snapshots below are taken from the standard UFGS scheduling specifications that are used for various agencies, including USACE, NAVFAC, AFCEC, NASA, and the VA.
From 01 32 01.00 10 (Project Schedule)
Schedule calendars are created within the scheduling program, such as Primavera P6, and allow the user to define working days and hours for each calendar.
Every schedule activity needs to have a calendar assigned. That calendar assigned determines which days that activity can take place.
Example 5-day weather calendar with anticipated adverse weather days blocked out
A 5-day weather calendar (5DW) calendar is a copy of the 5-day calendar, but includes additional days blocked out for anticipated adverse weather.
The number of days that need to be blocked out is typically included in the scheduling specification but can also be located in other parts of the Division 01 specifications, or another part of the contract.
Example 7-day calendar with no days blocked out
Schedule calendars applied incorrectly to activities
Schedule calendars that are applied to the wrong activities lead to faulty start dates, finish dates, and total float – compromising the overall accuracy of the schedule.
Scenario 3: The calendars are applied to the wrong activities.
Example 5-day weather calendar missing anticipated weather block-outs
Example 5-day calendar missing weekend and federal holiday block-outs
Now let’s illustrate the importance of schedule calendars on your schedule and what can happen if they’re incorrectly created or applied.
Scenario 1: The schedule calendars don’t block out required non-work days.
If the schedule calendar is missing the required blocked-out days, it’ll show activities taking place when the contract doesn’t allow.
For example, the snapshot below shows the 5-day calendar for the month of May that’s missing weekend block-outs and the Memorial Day holiday. Any activities assigned to this calendar will show work taking place on the highlighted weekends and federal holiday.
This can result in an overly optimistic schedule, or work that realistically couldn’t take place at the rate it’s shown. If the contractor doesn’t work those 4 weekend and holiday days highlighted below that are missing as block-outs, the work will fall behind 4 days that month.
Now consider if every month were missing days that needed to be blocked-out for the duration of the project – this effect compounds.
Schedule calendars that don’t block out required non-work days are overly optimistic with productivity, and therefore less reliable.
Schedule calendars are created within the scheduling program and allow the user to define working days and hours for each calendar that’s created. Each activity has to have a calendar assigned.
3 common schedule calendars include:
Errors in creating or applying the schedule calendar can result in the following scenarios:
Questions or comments? Reach us at connect@cpm-ss.com.
Thanks for reading.
Related Resources:
How to Learn Primavera P6 Quickly: A Beginner's Guide
Why Quality Construction Schedules Matter
Receive practical, actionable training and tools, including specialized templates and instruction for military and federal construction projects.
Have any questions?
We'd love to hear from you.
Get started for free with our collection of resources and in-depth articles on scheduling to enhance your success.
Feel confident in your project schedule by ensuring it’s reliable, contractually compliant, and utilized as a tool to minimize risk.
Whenever you’re ready, there are 3 ways we can help:
This blog is for general informational purposes only and is not to be considered an official interpretation or enforcement policy of the UFGS standard specifications. As individual project requirements vary, refer to your specific contract. See our Terms and Conditions and Disclaimer for additional information.
Starting with a new software can be quite intimidating, and Primavera P6 is no exception, especially if you're a newcomer. Traditional training methods can involve lengthy sessions, travel, and...
How to Learn Primavera P6 Quickly: A Beginner's Guide
Successful alignment of the project schedule and quality control system ensures a smooth start of the first phase of the 3 Phase Quality Control system. Also, it enables accurate monitoring of...
USACE Series Part 2:
Schedule and Quality Control
USACE Series Part 1:
Schedule and Progress Payments
The Schedule of Values and Construction Schedule are combined into a single Cost-Loaded Project Schedule, used to determine progress payments and provide placement projections...
Free Checklist
As the government or contractor, quickly and easily confirm your USACE schedule’s cost loading compliance with the 01 32 01.00 10 scheduling specifications.
Navigation
Legal
Offices located in West Granby, CT, and Forest Hill, MD
Founded in 2018 to specialize in schedule consulting and training for military construction.
Copyright 2024 CPM Schedule Solutions LLC. All Rights Reserved.
Contact Us